End in sight as two-year roadworks reach final stage
Roadworks in Attleborough have plagued the town for more than two years. Picture: DENISE BRADLEY - Credit: Copyright: Archant 2018
Roadworks which have plagued a town for more than two years are set to enter their fourth and final phase.
Designed to improve all forms of travel, the £4.5m Transport for Attleborough project has been affecting businesses, motorists and shoppers since it began in September 2018.
And work will resume next week, continuing for at least 17 weeks as contractors enhance cycling and walking facilities on London Road.
The scheme has so far been met with widespread derision, with drivers increasingly frustrated at road closures and firms complaining of a significant dent in trade.
Ahead of the final phase, Tim Cobb, who owns The Bakery on Church Street, argued businesses had suffered for long enough.
You may also want to watch:
“At this stage we just want it done with and finished,” said Mr Cobb. “The whole thing has gone on too long.
“I would say traders have lost around 25pc of their business every time the roadworks have happened. Around 10pc come back, but 15pc have gone elsewhere and stayed elsewhere.
Most Read
- 1 Town clerk sacked following months of controversy
- 2 'Sounded like my roof was coming off': RAF jet sonic boom heard over city
- 3 Norwich sonic boom: RAF confirms jet 'inadvertently' caused bang over city
- 4 Concern people are letting their guards down after getting Covid-19 jabs
- 5 Waits for second Covid jabs on target in our region
- 6 More than 1,000 laptops donated to children in need in campaign
- 7 Motoring giant pledges more than 600 brand new laptops to appeal
- 8 Norfolk MP denies breaking ministerial code by working for PPE firm
- 9 Landowners under pressure to stop repeat of floods
- 10 Bagpiper lifts spirits for care home residents on Burns Night
“The worst was the last set of roadworks where they pretty much blocked off the whole town centre. When it’s done it will be a big relief.”
Phil Leslie, mayor of Attleborough, added: “On the back of Covid and everything else that’s been going on, it will be a welcome relief to have the work completed.
“This has clearly been a significant issue but, finally, there is a light at the end of the tunnel.”
It is hope widening pavements on London Road and converting them to a shared pedestrian and cycling facility will ease journeys to the school, homes and the town centre. Existing-street parking will not be affected.
Improvements also include new paving, realigned junctions and a traffic light-controlled pedestrian and cycle crossing near to Chapel Road.
Restrictions during the work are as follows:
• London Road - November 23 for 17 weeks: Temporary parking suspension to prevent vehicles parking within the construction area.
• Chapel Road - November 23 for four weeks: Junction with London Road temporarily closed. Signed diversion route will be in place.
• London Road - dates TBC (towards end of construction programme): Closure of entire length of London Road for road resurfacing. Further details to be provided nearer the time.